Reconstruction of Road A14 Vilnius – Utena (km 59.00 – 64.332)

Featured image
Project title:

Reconstruction of Road A14 Vilnius - Utena (km 59.00 - 64.332)

Completed works:
Construction works
Type of construction:
Reconstruction
Fegda group companies:
Alkesta
Completed:
2025
Parameters:
Length of reconstructed road: 5332 km | Road width: 28 m

The existing concrete slab pavement was dismantled, and the main layers of the road structure were installed, including the earth embankment, frost-resistant layer and crushed stone base, followed by the laying of the asphalt pavement layer.

Water culverts were also installed.

Enlarged image